City facilities, powered in phases.

Project
Communications facilities power and distribution
Client
City of Jacksonville
Location
Jacksonville, FL
Value
$324K
Period
2023 – 2026
Status
Completed
Digger derrick truck lifting a light pole into place beside a parking lot

The brief

Twenty purchase orders across city departments since 2023. The electrical scopes: DC rectifier systems for communication towers, a 14 kW standby generator with a 200 A automatic transfer switch, switchboard and grounding upgrades, and power for eight concrete light poles.

Program stages3 stages
  1. Rectifier systems

    Supply, installation and hands-on operator training for DC rectifier systems supporting municipal communication towers.

  2. Generator and ATS

    Air-cooled standby generator with weatherproof enclosure and automatic transfer for critical communications infrastructure.

  3. Switchboards and grounding

    In-building electrical upgrades across multiple facilities: switchboard installation, receptacle additions and grounding improvements.

Challenges

What made it hard, and what we did about it.

Live communications infrastructure
Phased cut-overs with temporary power and verification at every step.
Many small scopes, one standard
The same documentation package on the smallest order as on the $188K switchboard scope, so the city's records stay complete.
Results

Results, as approved by the client.

purchase orders since 2023
20
awarded
$324K
concrete light poles powered
8
standby generator with a 200 A ATS
14 kW